AFCON 2027 Readiness Tracker: Every Stadium in Kenya, Tanzania and Uganda, Updated

CAF has confirmed the six host cities for AFCON 2027. Nairobi, Dar es Salaam, Arusha, Zanzibar, Kampala and Hoima will stage the tournament from 19 June to 17 July 2027. Here is every stadium, its capacity, how far along it is, and what is still to be done, with the date on each figure.

Photo by proudlyswazi / Unsplash

Table of Contents

CAF confirmed the six host cities for AFCON 2027 on Saturday, and for the first time the tournament has a map. Nairobi in Kenya, Dar es Salaam, Arusha and Zanzibar in Tanzania, and Kampala and Hoima in Uganda will stage the 36th Africa Cup of Nations, from 19 June to 17 July 2027, with 24 teams and the three hosts qualifying automatically. The announcement, made in a video on CAF's digital platforms, settles the geography. What it does not settle is the state of the stadiums, and that is where the next seven months will be decided.

This is the first edition of a tracker Sportblot will update as the deadlines fall. Every figure below carries the date it was reported, because on this build the numbers move every few weeks and the source matters as much as the percentage. A ministry figure is a builder's figure, not CAF's approval. In February 2026, CAF's first assessment found that none of the proposed venues in Kenya or Uganda fully met the confederation's top Category 4 standard. An inspection delegation then toured all three hosts for eight days in late August and early September. The final inspection is planned for January 2027, and that is the one that counts.

The seven venues, at a glance

Venue City Capacity Progress Status
Raila Odinga International Stadium Nairobi, Kenya 60,000 About 94% in October, 98% per the local organising committee in November Due to be commissioned 5 January 2027
Moi International Sports Centre, Kasarani Nairobi, Kenya 48,000 No figure given Renovation, handover due 31 December 2026
Benjamin Mkapa Stadium Dar es Salaam, Tanzania 60,000 About 95% in September Pitch being redone
Samia Suluhu Hassan Stadium Arusha, Tanzania 30,000 88% in September Final stage
Fumba Stadium Zanzibar, Tanzania 36,500 87% at end of October Due 31 December 2026
Mandela National Stadium, Namboole Kampala, Uganda At least 45,000 51% in October Running late, due end of March 2027
Hoima City Stadium Hoima, Uganda 20,000 Finished Opened 24 December 2025

One detail is still unclear in the first reports from Saturday. Kawowo names Fumba Stadium as Zanzibar's venue, while The Eastleigh Voice reports the New Amaan Complex as the listed venue. Zanzibar as a host city is confirmed. Which of its two grounds hosts matches is not yet settled in the reporting, and this tracker will correct the record when CAF's own venue list is published.

Kenya: the flagship is nearly there, the second ground is the worry

Nairobi hosts all of Kenya's matches, at two grounds on opposite sides of the capital. The new Raila Odinga International Stadium, built as Talanta Stadium on the old Jamhuri grounds off Ngong Road, holds 60,000 and is Kenya's first purpose-built football stadium. The figures for it disagree, and the disagreement is worth stating plainly. A Senate committee inspection in October put it at about 94 per cent. The local organising committee chairman, Nicholas Musonye, said this week it is 98 per cent ready. The government, through Interior Principal Secretary Raymond Omollo, has announced the stadium complete. All three can be true of different things: structure, pitch and operations are not the same milestone.

What is fixed is the date. The stadium will be commissioned on 5 January 2027 with a friendly between Bayern Munich and Ajax, announced by President William Ruto and confirmed by both clubs. Bayern called it the grand opening of the new national stadium. Tickets start at KSh 2,500. The match doubles as a dress rehearsal for the local organising committee, which is due to hand the facilities to CAF in January. Kenya hopes to stage the opening match and the final at the new ground. CAF has not decided either.

Kasarani is the harder case. The 48,000-capacity Moi International Sports Centre, north-east of the city centre, is being refurbished, and the project team still promises handover on 31 December. A Senate committee questioned the pace of the work on 11 November, after county officials told it the fire hydrants had no water at an earlier inspection. The pitch remains a concern for CAF, and Musonye said this week the ground would be usable by the end of January. The sports ministry has also warned the capacity may have to come down, because Kasarani stays the country's main athletics stadium. Nyayo National Stadium, near the city centre, is now listed as a possible training ground, and Eldoret's Kipchoge Keino Stadium has dropped out of the plans. Musonye said this week that Kenya is 99 per cent ready to host. That is his claim, not a verified fact, and Kasarani is the reason to treat it as one.

Tanzania: the furthest along, with one pitch to fix

Tanzania has the largest share of host cities, three of the six, and a CAF inspection early in 2026 found its preparations the most advanced of the three hosts. The Benjamin Mkapa Stadium in Dar es Salaam holds 60,000 and opened in 2007. Its renovation was about 95 per cent complete in September. The problem is the grass. In September, CAF inspectors judged the pitch not good enough for a Champions League match between Simba and RS Berkane, and the game was moved to the Amaan Stadium in Zanzibar. The pitch is being redone. CAF president Patrice Motsepe called the Mkapa "the ultimate mirror" of Tanzania's readiness, and said there is "no plan B" for the hosts.

The new Samia Suluhu Hassan Stadium in Arusha, in the Olmoti area, is designed for about 30,000 and was built by China Railway Construction Engineering Group at a reported cost of about $112 million. Government figures put it at 88 per cent in September, when Vice President Emmanuel Nchimbi toured the site, with its own training pitch past 60 per cent. Arusha is the gateway to the northern safari parks, and it is the smallest of the six host cities.

In Zanzibar, the new Fumba Stadium on the peninsula south of Stone Town is designed for about 36,500 and was 87 per cent complete at the end of October, with seats going in. It is being built by the Turkish firm ORKUN Group at a reported cost of about $147 million, and Zanzibar's government wants it finished by 31 December. President Hussein Ali Mwinyi said on 3 October that contractors had pledged to finish the AFCON projects by December. The older Amaan Stadium, in Zanzibar Town, holds about 15,000, reopened after a full renovation in December 2023, and was good enough for CAF to move the Simba match there. CAF has asked Tanzania to say whether it will be a match venue or a training ground.

Uganda: one finished, one nearly finished, one running late

Uganda's programme is the most spread out, and the most uneven. Hoima City Stadium, in the west, is the success story. The 20,000-seat ground opened on 24 December 2025, when President Yoweri Museveni commissioned it, after the Turkish firm Summa built it in about 14 months at a reported cost of about $131 million, funded from the Petroleum Fund. A CAF officer called it completed and commissioned in September 2026, with about 95 per cent of CAF's earlier list of fixes done.

The Akii-Bua Olympic Stadium in Lira, in the north, was 85 per cent complete at the end of October, with handover set for January 2027. It is named after John Akii-Bua, Uganda's 1972 Olympic 400 metres hurdles champion, whose world record of 47.82 seconds still stands as one of African athletics' great marks. But Lira was not included in CAF's final selection of host cities on Saturday, so Akii-Bua now looks like a training and legacy venue rather than a match ground. Its reported cost is about $129 million.

The problem is Namboole. The Mandela National Stadium, about 10 kilometres east of central Kampala, is the furthest behind of all seven venues. The UPDF Engineering Brigade, the army's engineers, is rebuilding it with more than 3,600 workers. In October, the project engineer told MPs it was 51 per cent done and promised completion by the end of March 2027. That is already three months past the original target of 31 December 2026, and the chairman of Uganda's sports council has mentioned a revised target of the end of June, which would fall after the tournament's opening match on 19 June. The rebuilt ground is planned for at least 45,000 seats, above CAF's 40,000 minimum for a Category 4 stadium. The second phase of the work is reported to cost USh 248 billion, about $59.5 million, after a first phase reported at USh 97 billion, about $23.3 million. A parliamentary committee that toured the site in October left frustrated at the pace. Namboole is the one venue where the question is no longer whether it will be ready on time, but what happens if it is not.

What happens next

The calendar from here is fixed, and it is short. The 31 December deadline covers most of the remaining works, including Kasarani, Fumba and Akii-Bua. The Raila Odinga International Stadium is commissioned on 5 January, with Bayern against Ajax as its first match. CAF's final inspection follows in January, which Motsepe has said he will lead himself. The last qualifiers run from 22 to 30 March 2027, when the 24 teams will be known, and the draw and match schedule follow. The opening match is on 19 June.

Two things beyond the stadiums are still to be settled. No decision has been made on where the opening match or the final will be played, and a proposed single East Africa entry visa for fans had not been agreed between the three governments as of October. Tickets had not gone on sale as of October either.

There is also the question nobody in the three capitals wants to ask yet, and one voice has already raised it. Paulo Cruz, founding chief executive of African Collaborations Group, told Business of Sports Africa that the hosts should plan now for what happens to the stadiums after the tournament, using Namboole as his example. The Uganda Premier League draws average attendances of 3,000 to 5,000 per match, according to one analysis of the programme, and Uganda's combined public investment across its three stadium projects is reported at more than $300 million. The same arithmetic applies, in smaller measure, in Arusha and Hoima.

That is the second half of this story, and it will matter long after the final whistle. For now, the first half is nearly written. Six cities are confirmed, seven grounds are on the list, one is finished, and one is half built with seven months to go. East Africa has waited since Ethiopia hosted in 1976 for the Cup of Nations to come home. The stadiums will decide whether the wait ends in June, or whether the tournament arrives before its grounds do.

Sportblot will carry the continental story from here.